How to price and bid HVAC jobs
Price the whole HVAC replacement, from specified equipment and removal to testing and handover. Follow a sample bid built from costs, overhead and markup.

Before you start
- Price a confirmed system specification and the work needed to install it.
- Include removal, connections, testing, subcontractors and job fees alongside equipment.
- Separate job costs from your customer price, then make the bid scope clear.
To price an HVAC replacement, confirm the scope first, then add up equipment, labor and other direct costs from real quotes. Add your share of overhead, apply the markup you've chosen, and write a bid that says what's included, what isn't and how changes get handled. A worked example with hypothetical USD figures follows.
This guide covers a planned replacement. A service call works differently. Price the diagnostic visit separately, then quote the repair once the fault and required work are clear. A planned replacement has a defined scope you can price before you start.
Confirm what the replacement includes before you price it
Equipment is only part of the job. ENERGY STAR's quality-installation guidance treats a good install as more than swapping boxes. The system should be sized to the actual building, the ducts should be evaluated, and the system should be checked at startup. Each of those takes time, so each belongs in your price.
ACCA makes a related point about existing homes. A replacement should rest on a known building load, and installed performance should be measured and documented. Existing load records may still apply if the building and duct system haven't changed. The point is that you know the load, not that you guess from the old nameplate.
So before the bid is firm, a qualified HVAC assessment should settle four things:
- The matched system and its capacity
- Whether the existing ducts are suitable to reuse
- Whether the existing electrical supply is suitable to reuse
- The specified work that follows from those answers
If the assessment turns up a known upgrade, price it as its own line now. A panel upgrade or a section of duct replacement should not hide behind a vague "other work excluded" clause. If something unexpected turns up after you start, you handle it through an agreed change in scope and price. Writing the scope down in detail helps here, and our guide on how to write a construction scope of work covers that.
Build the price from quotes: equipment, labor and other costs
Equipment and accessories. Price the named, specified items, including the model references, controls and accessories. When you get the supplier quote, check four things:
- How long the quote is valid
- Whether freight is included
- What's in the package: pad, condensate parts, control, duct transition
- Who is responsible for what
Validity periods vary by supplier, so read yours rather than assuming one. A quote that expires before the customer signs can leave you eating a price change.
Labor. Count person-hours for each person, not elapsed days. Two people working eight hours each give you 16 person-hours. Use loaded labor cost rates, meaning wages plus employment costs, but not overhead or profit, since you add those later. Include your own time if you're on the tools. Our guide to estimating labor costs goes deeper on rates and hours.
Other costs. Give each its own line:
- The electrical subcontract
- Delivery
- Disposal and recycling fees
- Handling equipment hire
- A permit and inspection allowance
Keep removal labor and disposal fees apart. Taking the old equipment out is your crew's time. The fee to get rid of it is a separate charge, and it can change without your hours changing. Include time for permit coordination and inspections where needed. In the example below, that time is included in the survey and closeout hours.
This is where an estimate gets tedious to assemble by hand. With Construction Job Estimator, you describe the job by voice or text, add the measurements you've taken and your site photos, and it builds a working estimate. You can pull real-time material prices from local suppliers, compare supplier options, or enter a quote you already have. Materials, labor and other costs like delivery, equipment hire and disposal sit in one estimate with editable markup. You can review the quantities, prices and hours, adjust the figures and prepare a professional estimate or quote in minutes. The HVAC estimating app page has more detail.
Worked example: replacing one assessed ducted heat-pump system
The scope: Replace one residential ducted heat-pump system. It includes a specified matched outdoor unit, a specified indoor air handler, a compatible control, and a specified connection and accessory package. Your crew removes the old equipment, installs the new, commissions it and hands it over. The outdoor spot is accessible at ground level, and the indoor utility area is accessible too. The existing main ducts and electrical supply were assessed as suitable. The price excludes crane work, major duct replacement, a panel or service upgrade, structural repairs and hazardous-material work.
These are hypothetical USD costs, hours and allowances. Use your own costs for your job. Cost entries are assumed to include any purchase taxes you can't recover, and the bid is shown before applicable tax.
Materials and other costs
| Item | Cost (USD) |
|---|---|
| Specified matched outdoor unit and indoor air handler | 4,000 |
| Connection materials, pad, condensate parts, minor duct transition | 450 |
| Compatible thermostat/control | 150 |
| Materials | 4,600 |
| Electrical subcontract (agreed connection work, no panel upgrade) | 450 |
| Equipment delivery | 125 |
| Disposal/recycling fees | 175 |
| Handling equipment hire | 150 |
| Permit/inspection allowance | 200 |
| Other costs | 1,100 |
The $200 permit line is a sample allowance. Check which approvals your job needs and replace it with the actual fee, or remove it if none applies.
Labor
| Role and hours | Cost (USD) |
|---|---|
| Lead: 20 hours × $45 | $900 |
| Helper: 16 hours × $30 | $480 |
| Total: 36 person-hours | $1,380 |
That's 36 person-hours across two people, not 36 hours each. The hours break down like this:
- Survey, specification review and ordering: 3 lead, 0 helper
- Removal and positioning: 4 lead, 4 helper
- Equipment and connection installation: 8 lead, 8 helper
- Startup, testing and customer handover: 4 lead, 2 helper
- Cleanup and closeout: 1 lead, 2 helper
The electrician's time is inside the $450 subcontract line, so it isn't in these hours.
Direct cost and overhead
Materials of $4,600 plus labor of $1,380 plus other costs of $1,100 gives a direct cost of $7,080.
Then add $600 of allocated overhead. That covers business costs not already inside your loaded labor rates, material prices, fees or the subcontract. Count it once. If you've already built insurance or truck costs into your labor rate, don't charge them again here. Your cost including overhead is $7,680.
Add profit and check what your markup really does
Markup is the percentage you add on top of cost. This example uses 25%, which is a choice for this job, not an industry norm.
25% of $7,680 is $1,920. Add it and the bid before tax is $9,600.
Markup and margin are different numbers. That $1,920 is 25% of your cost but 20% of the $9,600 price. A 20% margin on this full cost base is not a guarantee of net profit. Your actual result still depends on whether the job runs to the hours and costs you priced. Our contractor markup calculator lets you test other percentages.
Don't add markup to a rate that already includes markup, or you'll count profit twice.
Write the bid so the customer knows what they're getting
Your customer needs to know which equipment you're supplying and what the installation price covers. Fill in the model references, control, connection work and any agreed accessories from your supplier quote. Keep your internal wage rates and overhead calculation in your costing sheet.
Include required upgrades in the base scope and total. Show genuinely optional upgrades separately so the customer can choose them without removing work the system needs.
Then say what happens if something unexpected shows up. Document the condition and agree any extra scope and price before carrying out the additional work. Tie the bid's validity window to your supplier quotes, so you aren't holding a price longer than your supplier holds yours.
A short version for this job might read:
Replace the existing ducted heat-pump system with the specified matched outdoor unit, air handler and compatible control. Includes connection and accessory package, agreed electrical connection, removal and disposal of old equipment, delivery, handling equipment, permit allowance, startup, commissioning and handover. Existing main ducts and electrical supply assessed suitable for reuse. Excludes panel or service upgrade, major duct replacement, structural repairs, hazardous-material work and crane work. Price: $9,600 before tax. Unexpected conditions will be documented and agreed in scope and price before extra work begins.
Fill in the actual model selections, payment terms and quote validity date before it goes out.