How to Bid on Commercial Landscaping Jobs

Build a commercial landscaping bid from the site scope, seasonal visits, crew hours and equipment costs. Separate maintenance contracts from installation work.

3D landscaping contractor planning grounds maintenance at a commercial property

Before you start

  • Separate ongoing maintenance from one-off installations.
  • Use the service calendar to calculate crew hours and job costs.
  • Make billing terms and extra-work approval clear.

A commercial landscaping bid starts with the type of work. One is a recurring grounds maintenance contract, priced across a season or a year. The other is a one-off installation, priced as a single project. Decide which one you're pricing before you open a calculator, because the math is different.

Maintenance depends on how many visits the property needs, what you do on each one, and what the work costs you over the whole term. Installation depends on quantities, phases and materials. The Landscape Institute publishes maintenance contract resources separately from its construction material, which fits how most contractors already treat the two.

Most of this guide covers maintenance, where repeated visits need to be priced across the full service term. There's a short installation section near the end. For the general approach to installation pricing, see how to price landscaping jobs.

Get the site details and service specification before you price

Ask the client for a site plan and a written service specification. If they don't have one, walk the property and write down what you're being asked to do. Then confirm that list with them in writing. Get agreement on the scope before treating your price as firm.

Measure the areas you'll price: turf, beds, hedges and edge lengths. While you're there, check these things, because each one changes your hours or your costs:

  • Access, parking and where you can unload
  • Where green waste can go, and what disposal will cost you
  • Working hours and any site restrictions
  • Who is responsible for irrigation, trees, snow and any specialist work

That last item is where bids go wrong. If the client expects you to handle something, either price it or agree in writing that someone else will. Quietly leaving required work out of your price only creates a dispute later. An exclusion doesn't satisfy a requirement the client has put in the bid.

If you want to turn those measurements into a working number quickly, you can describe the job to Construction Job Estimator by voice or text, include the measurements you've taken, and add site photos. You supply the measurements. The app uses them to build a working estimate you can review and adjust.

Build a seasonal task and frequency calendar

List every service by season: mowing and edging, bed maintenance, pruning, seasonal cleanups and anything else the specification names. Next to each one, write how often it happens. Take that number from the specification and the property, not from a habit.

Don't start from a standard weekly pattern. Turf grows at different rates across the year, some clients want fewer visits in the off season, and some sites need more attention in certain months. The count could be 30 visits, or it could be something else entirely. Let the specification and the site decide it.

Keep routine visits and seasonal tasks apart. A spring cleanup that happens on its own day gets its own hours. A cleanup folded into a routine visit is already covered by that visit's hours, so counting it again inflates your price. This calendar is also what the client will read, so it tells them what they're getting and roughly when.

Cost one visit, then roll it up to an annual maintenance bid

Start with person-hours. That's the hours worked by each person, added together, and it's different from how long the crew is on site. Two people on site for 1.5 hours each is 3 person-hours, and paid travel and setup add to that. Include paid travel, unloading and cleanup. Then add equipment operating costs, materials and waste.

Once you've costed the visits, add the seasonal work, then allocated overhead, then your markup. Markup is a percentage added on top of your cost to get your price. It isn't the same as margin, which is profit as a share of the price. You can check the numbers with the contractor markup calculator.

Here's a worked example for one small commercial property. These are sample prices in USD. Use your own costs for your job.

Line Amount
30 routine visits × 4 person-hours (two people, each 1.5 h on site + 0.5 h paid travel and setup) 120 hours
Separately scoped seasonal visits 24 hours
Total labor 144 hours
Labor at $30 employment cost per hour $4,320
Equipment and fuel $900
Materials $480
Disposal $300
Direct costs $6,000
Allocated business overhead $1,200
Your cost $7,200
25% markup $1,800
Annual bid, before any applicable tax $9,000

Before you send a number like this, check it for double counting. The 24 seasonal hours must not overlap with the 120 routine hours. Equipment and fuel are cash operating costs, so they stay out of the labor line. Overhead goes in once, as a single allocated amount. Also, the $30 is an employment cost per person-hour, not the rate you charge the client.

A 25% markup on $7,200 is $1,800. That's 20% of the $9,000 price, so your margin is lower than your markup. Mixing the two up is a common way to price too low.

Construction Job Estimator can hold materials, labor, equipment, disposal and markup in one estimate, and you can review and edit each line. When your bid includes materials such as mulch, plants or edging, it can pull real-time material prices from local suppliers. That lets you compare supplier options or enter a price you already have.

Set billing terms, weather rules and extra-work approval

Monthly invoicing is a billing choice. It doesn't mean the work arrives in equal monthly pieces. If the contract in the example above splits the $9,000 into 12 equal installments, the client pays $750 a month. Your visits still follow the service calendar, with more in some months and fewer in others. Say so in the bid so nobody expects a visit every month because they were billed every month.

Decide with the client how weather delays and missed visits are handled. Will a rained-out visit be made up, skipped, or combined with the next one? Whatever you agree, write it into the terms. It's much easier to settle this before the first rainy week than during it.

Do the same for extra work. If a storm drops debris or the client adds an area, say how they request it, how you price it and who approves it before you start. A short sentence in the bid does the job. You don't need a legal essay, and the right wording depends on your client and your contract.

If you're bidding a one-off installation instead

An installation bid uses a different method. Take off quantities from the plans or your site measurements, then break the job into phases such as prep, planting, hardscape and cleanup. For the single project, price materials, labor, equipment, delivery, disposal and overhead, then add your markup.

There's no annual multiplication and no visit calendar. The price covers the defined scope, so the scope needs to be precise. For the fuller approach, use how to price landscaping jobs.

Check purchased quantities and delivery costs against each installation phase before sending the price.

What to put in the client submission

Follow the client's submission format if they give you one. If they don't, a complete bid covers these points:

  • Scope and service specification: what you'll do and where
  • Assumptions: measured areas, access, disposal arrangements and anything else the price depends on, written plainly so the client can check them
  • Schedule or calendar: the seasonal tasks and visit pattern
  • Exclusions: anything outside the price, such as work another party handles
  • Extra-work approval: how additions are requested, priced and approved
  • Price and billing terms: the annual or project price, and how it's invoiced
  • Validity: how long the price stands
  • Insurance: include it as the client actually requests, not as a default

The practical order is simple. Build the cost from the calendar, check for overlap, add overhead and markup, then send a professional estimate or quote. Construction Job Estimator can prepare that quote from the figures you've checked, so you're not retyping them into a separate document.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors