How to estimate concrete work: quantities, labour and price

Estimate concrete volume, bag quantities and the full job cost with a worked slab example. Separate material orders from labour and selling price.

3D contractor checking timber slab forms beside aggregate, concrete bags and a wheelbarrow

Before you start

  • Calculate specified concrete volume separately from excavation and base.
  • Check supplier order increments and the actual mixed yield of bags.
  • Include preparation, placement and finishing before adding overhead and markup.

A concrete estimate needs two connected calculations: the amount of concrete to order and the cost of delivering the complete job. A correct cubic-yard figure still leaves forms, base preparation, reinforcement, access, placement and finishing to price.

Use the concrete calculator for quantities and the concrete estimate template to present the work. The figures below are illustrative inputs, not local market prices.

Inspect and define the pour

Record the footprint, specified thickness, finished levels, access and finish. Identify which drawings or instructions define the mix, reinforcement and joints. An estimating worksheet does not decide those design requirements.

Ask where the delivery vehicle can reach and how concrete will move from the delivery point to the forms. Include protection, washout arrangements, equipment and reinstatement where they belong in your scope. State how unsuitable ground or concealed services will be handled if discovered.

Keep concrete depth separate from excavation depth. A deeper excavation may also contain a base layer; multiplying the full excavation depth by the slab footprint can overstate the concrete quantity.

Calculate the concrete volume

For a rectangular slab, multiply length by width by thickness in matching units. In this example:

  • Length: 12 ft.
  • Width: 10 ft.
  • Concrete thickness: 4 in, or one-third of a foot.
  • Volume: 12 × 10 × 4 ÷ 12 = 40 cu ft.
  • Cubic yards: 40 ÷ 27 = 1.481 cu yd.

Calculate thickened edges, steps and separate footings individually, then add their volumes. Do not count a thickened edge in full if part of it is already included in the main slab calculation.

For a metric example, 4 m × 3 m × 0.1 m is 1.2 m³. This is a separate example, not a conversion of the 12 × 10 ft slab.

Convert volume into an order

Suppose you choose a 10% allowance for the illustrative slab. The quantity becomes 44 cu ft, or about 1.630 cu yd. Confirm the supplier’s ordering increments, minimum delivery and charges before placing the order.

If a selected bag produces 0.6 cu ft of mixed concrete, 44 ÷ 0.6 = 73.333 bags, rounded up to 74 bags. Use mixed yield from the actual product. Bag weight alone is not a volume. QUIKRETE’s calculator is a useful product-specific check.

Bulk and bagged concrete are alternative supply methods. Compare the total logistics and labour of each; do not add both material quantities to the same estimate.

Price the work around the concrete

Break the job into preparation, base, forms, specified reinforcement, delivery, placement, finishing, curing provision and cleanup. Keep person-hours separate from elapsed calendar time. Two people working eight hours use 16 person-hours; a period of curing is not automatically continuous paid attendance.

The rebar calculator can check quantities from a supplied layout. It does not choose bar size, spacing or lap lengths.

Work from your costs to the price you send

A sample cost breakdown might be concrete supply 315, base 180, forms and reinforcement 240, 16 person-hours at 35 for 560, and delivery or equipment 150. These are sample prices in USD; use your own costs for your job.

Direct cost is 1,445. A 10% overhead allowance adds 144.50, which brings your job costs to 1,589.50. A 20% markup, meaning 20% added on top of those costs, adds 317.90. The price you send your customer is 1,907.40 before tax.

Use your own job costs, and don't add overhead twice if your labour rate already covers it. For Canada, obtain CAD quotes; selecting CAD does not exchange USD figures.

The slow part of this build-up is usually pricing each line from scratch: concrete, base, forms and reinforcement, then labour and delivery alongside them. Construction Job Estimator is built for that step. You describe the pour by voice or text and add site photos, and it puts together a working estimate in minutes using real-time material prices from local suppliers. Materials, labour and other job costs sit in one estimate. You can see the quantities, prices and labour behind each figure and adjust them, so you can check the result against your own numbers. When it looks right, you can prepare a professional quote for your customer and convert it to an invoice once they accept.

Send a scope the customer can check

State dimensions, thickness, finish, inclusions, exclusions, validity and payment arrangements. Explain any unresolved selection or ground-condition assumption. Save the accepted revision before ordering.

If you'd rather lay the scope out in a document you can edit, start from the concrete estimate template.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors