How to price cabinet installation jobs
Work out what to charge for fitting cabinets, from the first site check to the final adjustments. Include the small tasks that can take a big bite out of your price.

Before you start
- Price the full installation scope, including fillers, panels, hardware and cleanup.
- Count person-hours and job costs before adding overhead and profit.
- Use per-cabinet or linear-foot rates only for a clearly defined scope.
To price a cabinet installation job, list what's on the layout, add up the person-hours, add each job cost once, then apply your markup. Check the total against a per-cabinet or linear-foot figure from your own finished jobs. This guide covers installing cabinets that are already specified and supplied. Building or quoting custom cabinets is a separate job.
The sample below uses sample USD costs, so swap in your own. If you'd like a document to adapt as you go, the cabinetry estimate template is a starting point. The downloads include a supply-and-fit laundry sample; the page also shows a customer-supplied kitchen installation example using the same $2,225 total as this guide. Adapt the blank rows and supply responsibilities to your installation.
Decide who supplies what before you count anything
Install-only and supply-and-fit are two different prices, so settle this first. Write down who provides the cabinets, doors and drawers, fillers, end panels, toe-kick material, handles, countertops and consumables. This is a scope decision for each job. Don't assume it.
Preassembled boxes still take real work. You position, level and fix them, fit the fronts and handles, and make adjustments. Flat-pack cabinets add assembly, which should be its own line in your hours. Don't bury it in the install time.
In the sample job, the customer supplies the cabinets, doors, drawers, two filler blanks, two end panels, toe-kick material and 12 handles, all checked and on site. You supply only the consumables. The estimate says exactly that.
Then list what's left out. For this job that means cabinet assembly, removal and disposal of old cabinets, major wall or floor repairs, countertop supply and fitting, plumbing, electrical work, appliances and painting. That gives your customer a clear view of what the price covers.
What to count from the layout and the site
Count from the agreed layout by type: base units, wall units, tall units and islands. Then add the finish pieces: fillers, end panels, toe kick, handles and any trim. Note whether each unit arrives preassembled or flat-pack. Six base and four wall cabinets with no talls or island is a very different job from the same count with a tall pantry and an island.
IKEA's kitchen installation guide splits the work into cabinet assembly, cabinet installation, fillers, and doors and drawers. It also tells installers to check the wall and floor condition and the delivered items. Those make good separate lines in your own hours. Fillers give doors and drawers clearance, and they can need fitting to an uneven wall, so don't price them as an afterthought.
Treat each site check as a pricing decision:
- Access and room condition: If the room isn't cleared, decide whether clearing it is in your price or someone else's job.
- Walls and floors: Price the ordinary fitting the job needs. Put major repairs in the exclusions or a separate agreement. Check the manufacturer's requirements for the system you're installing.
- Delivered items: Check the delivery against the layout before you price. A missing or damaged piece can mean another trip, and the estimate should say who pays for it.
Leave time for final adjustments. KraftMaid's adjustment guidance treats hinges, drawer fronts and runners as separate adjustments, which is a good reason to give them their own hours rather than assuming they happen on the way out the door.
Agree shortages and customer changes in the scope or as a change price, and include any extra trips they cause. Fixing your own installation defects is a different matter. Don't present that as an automatic extra.
Worked example: build the price from hours, costs and markup
Person-hours are the hours each person works, added together. Two people working eight hours each is 16 person-hours. Your own labor counts, even if you aren't paying yourself a wage on the job.
Here are the hours for the sample job: six preassembled base cabinets and four preassembled wall cabinets in a cleared room.
| Task | Person-hours |
|---|---|
| Site check and job planning | 3 |
| Protect room and unpack/check units | 3 |
| Set out, level and secure units | 14 |
| Fit supplied fillers, end panels and toe kicks | 4 |
| Fit handles and adjust doors/drawers | 4 |
| Travel, cleanup and handover | 4 |
| Total | 32 |
Planning and travel wages are already inside those 32 hours. Don't add them again as separate costs.
The sample uses $40 an hour as your labor cost, including the employment costs that apply. That's what an hour of labor costs you. It isn't the rate you bill. So 32 person-hours at $40 is $1,280.
Now add the other job costs, each one once:
| Cost item | Sample cost (USD) |
|---|---|
| Labor (32 person-hours × $40) | 1,280 |
| Consumables | 120 |
| Vehicle and travel allowance (excludes wages) | 80 |
| Equipment | 60 |
| Allocated overhead (excludes direct job costs listed above) | 240 |
| Total cost | 1,780 |
The vehicle allowance covers the vehicle only, because the travel wages are already in your labor. The overhead line covers your general business costs only. Anything already listed above it stays out.
Apply a 25% markup, which is a percentage added on top of cost. That's $445, so the price before tax is $2,225. The same job gives a 20% margin, because margin is your profit as a share of the price ($445 ÷ $2,225). Those are two different numbers for the same profit, so pick one and use it consistently. The contractor markup calculator converts between them, and the guide to estimating labor costs goes deeper on the hours.
Test the price with one change. Add 4 person-hours at $40 and $40 of extra supplies, and your cost rises by $200. With other costs and overhead unchanged, the 25% markup gives $2,475, which is $250 more. If the change also means more travel or more overhead, add those only if you'd really incur them.
Rebuilding this by hand for every layout is the slow part. Construction Job Estimator lets you describe the job by voice or text and add site photos to get a working estimate. Labor, materials and other job costs sit in the same estimate. You can see the quantities, prices and labor behind each figure and change them, so your own hours and costs stay in charge. The aim is an accurate, professional estimate in minutes. If you're supplying any materials yourself, you can price them with real-time material prices from local suppliers.
Fixed job, per-cabinet or linear-foot pricing
All three can work. They suit different scopes.
Fixed job price. This fits a defined layout and scope, like the sample. You build it from hours and costs, then present it as one number. It's the most direct way to price a job like this because it follows the actual work.
Per-cabinet price. This works when the units are similar in size and fitting effort. It gets shaky when tall units, fillers, panels or awkward walls change the work from one box to the next. The sample comes to $2,225 for 10 cabinets, or $222.50 each. That's a result of this job's numbers, not a rate to reuse on the next one.
Linear-foot price. A base run and a wall run aren't automatically the same linear-foot scope. Decide whether you measure each run separately, and what the foot includes. Fillers, end panels and toe kick are the usual questions. Write the answer into the estimate so you and the customer count the same thing.
Whichever shortcut you like, calibrate it from your own completed jobs of a similar kind, using the hours and costs you recorded. Use it to check the bottom-up number, not to replace it. If the two disagree by a lot, find out why before you send the price.
Turn the price into a customer-ready estimate
Write the scope the way your customer will read it. Say what you'll install, what the customer supplies, what you supply, and what's excluded. A reader who sees "customer supplies cabinets, doors, drawers, fillers, end panels, toe-kick material and handles" knows where your price starts and stops.
Say how unresolved repairs, shortages and customer changes will be handled: a separate agreement or a change price. Payment terms, how long the price stays valid and how the customer accepts it are yours to fill in. Complete those for your own business, and don't copy them from a sample.
Once the figures are in Construction Job Estimator, you can prepare a professional estimate or quote from them to send. When the customer accepts, you can convert the estimate into an invoice, then review the invoice against the work and any agreed changes before sending it.
For the next job, follow the same order: scope, counts, hours, job costs, markup, then a check against your shortcut. When it's done, save your actual hours beside the estimate. Those records are what make your per-cabinet and linear-foot checks worth trusting.
Building the cabinets as well? See how to quote custom cabinets for design, fabrication, hardware and finishing costs.