How to price construction change orders without missing costs
Price extra construction work with clear additions, credits, labor and markup. Follow a worked change-order example and avoid charging twice.

Before you start
- Price only the scope that changed.
- Show additions and credits clearly.
- Apply the markup treatment in your agreement.
To price a construction change order, describe exactly what changed, add up the direct costs it creates, subtract credits for any work that comes out, and apply markup only if your contract supports it. The same method works for additions, substitutions and omissions. The example below uses sample USD figures, so swap in your own costs.
Step 1: Write down what changed and what the original price already covers
Start with a sentence or two your customer would recognize, such as "Replace the specified base trim with the upgraded profile in the hallway and two bedrooms." If your original scope was vague, that's usually where change-order arguments begin. Our guide on how to write a construction scope of work covers how to make it clearer.
Then check the original contract or estimate. AIA's fundamentals of change orders advises confirming that the changed work isn't already required before you price it. The same source advises against duplicating overhead. In practice, don't charge again for setup, mobilization or overhead that's already inside the original price.
If the change replaces something, note what comes out as well as what goes in. That's how credits get remembered. If an allowance is involved, see how to include allowances in construction estimates.
Step 2: List every direct cost the change adds
Go through the categories one at a time instead of pricing from memory:
- Materials: the new items, plus any fasteners, adhesive or finishing supplies they require.
- Labor: hours for each person on the change, including time that wasn't in the original estimate.
- Delivery: an extra trip or a separate order is a real cost.
- Equipment hire and disposal: removed material often needs hauling, and a tool rental can belong to the change alone.
- Permits or other fees: only if this change triggers them.
Count person-hours, not elapsed time. Two people working three hours on the change is six person-hours, even if the clock only ran for three.
For a cost-plus-markup calculation, use your labor cost rate. If your agreement uses final billing rates instead, use those and avoid adding the same overhead and profit again. Give every cost a real figure. If you're leaving something out on purpose, say so on the change order instead of writing a vague "allow something."
Add the lines together to get your net direct addition. Don't apply markup yet.
If you'd rather describe the extra work than rebuild every line by hand, Construction Job Estimator can turn your job details, measurements and site photos into a working estimate. It brings in real-time material prices from local suppliers and keeps labor and other costs together. Review the quantities, rates and markup before sending your customer the price for the added work.
Step 3: Decide whether markup applies
Markup is the percentage you add on top of your direct costs to cover overhead and profit. Whether you can add it to a change, and how much, depends on your signed agreement. There's no universal 20% you're owed. AIA's article on overhead and profit on deductive and net-increase change orders shows how rules for net increases and deductions are set by the contract, so read yours.
Check three things before you send a price:
- What markup percentage, if any, the agreement allows on changes.
- Whether it applies to a net increase or only to added items.
- How it treats credits for omitted work.
Also confirm whether the contract means markup (a percentage added to your cost) or margin (a percentage of the final price). They aren't the same. On $490 of direct cost, a 20% markup adds $98. A 20% margin would make the price $612.50. And if your markup already covers overhead, don't add a separate overhead line on top.
Worked example: a trim change that takes an $8,000 job to $8,588
Say the customer adds trim to a previously untrimmed hallway after the contract is signed. The original scope did not include this hallway trim. These are sample prices in USD; use your own costs for your job.
| Line item | Amount (USD) |
|---|---|
| Additional trim materials | $180 |
| Labor: 6 person-hours at $45 cost per hour | $270 |
| Extra delivery | $40 |
| Net direct addition | $490 |
| Agreed markup, 20% (this example only) | $98 |
| Change order total, before applicable tax | $588 |
The original contract was $8,000 before tax, so the revised contract is $8,588 before tax. Keep both amounts on the same tax basis. No omitted-work credits apply here, because nothing came out of the job.
The 20% is the markup agreed in this example. It's not a standard. If your contract says something different, use that.
Substitutions and omitted work: show additions and credits separately
Before promising a credit, check whether ordered materials can actually be cancelled or returned, and account for any agreed return or restocking costs.
A substitution has two sides. List what you're adding and what you're taking out on separate lines, so the customer can see the new cost and the credit side by side. If you net them into one number, the customer can't check your math and you can't check your own.
Work out the net direct change first. Then apply whatever your agreement says about two points: whether omitted work carries overhead and profit, and whether markup applies to the net increase or only to the added items. Don't guess at these. The AIA source above shows that the answers vary by contract.
Record the schedule effect and keep the versions together
State whether the change affects a return visit, delivery, completion date or another trade. If timing is unchanged, say so. If a lead time is unresolved, identify what must be confirmed before you promise a date.
Keep the original estimate and the change reference together. Record the required approval under the project's agreed change process before the changed work starts. Our construction change order template gives you a place to record the scope, additions, credits and revised total.
When you invoice, identify the accepted change and check that its additions are charged once and agreed credits are included. Reconcile payments already received; the contractor invoice template separates charges, payments and balance due.
A quick check before you send it
Read the change order once as the customer would. Is the changed scope described in plain words? Is anything already in the original price being charged again? Are all direct costs listed, including delivery, disposal and extra hours? Are credits on their own lines? Does the markup match your contract? And have you handled tax the way it applies to your job?
If every answer is yes, the number is ready to go.