How to include allowances in a construction estimate

Show allowances clearly in your construction estimate. Define what each amount covers, set selection deadlines and adjust for higher or lower final costs.

3D contractor and customer comparing bathroom finish samples beside an unfinished vanity

Before you start

  • Define exactly what each allowance covers.
  • Separate selection allowances from contingency.
  • Replace provisional costs with final costs without double charging.

To include an allowance in a construction estimate, give it its own line. Name the item, say what the amount covers, set a date for the customer's choice, and write down how you'll settle the difference if the final cost lands above or below the number. Here's how to do each part, with a worked example.

What an allowance is and what it isn't

An allowance is a defined provisional amount for one identified item whose final selection or cost isn't settled yet. A vanity, a light fixture or a tile choice are typical. You price the job with a placeholder, then adjust once the customer decides.

Two other things get mixed up with allowances:

  • Contingency covers uncertainty in the work itself, like hidden conditions behind a wall. The selection allowance in this guide covers an identified item whose choice or cost is not yet settled. Keep them on separate lines so one doesn't quietly absorb the other.
  • A customer upgrade is a choice above what your base price already includes. It only counts as an allowance overage if your agreement says so.

There's no standard allowance amount. The number should come from your own costs and what your customer is likely to pick.

Write the allowance line so the customer knows what it covers

A vague line like "Vanity allowance: $600" invites an argument later. Spell out three things.

The item and its basis. Name the item, the quantity and the spec you priced, such as one 30-inch single-sink vanity. The customer should see what $600 buys.

Material only or installed. Say whether the amount is the purchase cost alone or includes installation. In the example below, it's purchase cost only, and installation sits in your base price. That installation price holds only if the work stays the same. A different vanity size or a new plumbing layout changes the work.

Delivery, tax, labor and markup. Decide whether each one sits inside the allowance or on its own line elsewhere in the estimate. Then write it down. A customer who sees delivery in two places will assume you charged for it twice.

This is where line-by-line detail pays off. In Construction Job Estimator, the allowance can be its own line item. You can see the quantity, price, labor and markup behind it, and adjust each one. If you already have a price from your supplier, you can enter it. You end up with a professional estimate or quote where the allowance reads as a separate line, not buried in a lump sum.

Set a selection deadline and tell the customer plainly

An allowance only works if the choice gets made. Tie the deadline to when you need to order, not to a loose phrase like "before we start." If a vanity takes weeks to arrive, the deadline is that many weeks before you plan to install it.

Put the deadline and the allowance amount in the wording the customer reads and signs. A conversation on site is easy to forget. A line on the estimate isn't.

You can also say what happens if the choice comes late, such as the install date moving. Only write consequences your contract supports. Don't add legal-sounding penalties you haven't built into your agreement.

Worked example: a vanity allowance above and below budget

These are sample prices in USD, before tax. The 20% markup and the two-way settlement are an example agreement, not a universal rule. Use your own costs and contract terms.

Set-up: Your estimate includes a $600 purchase-cost allowance for a vanity plus $120 markup on that allowance, so the original price includes $720 for this item before tax. Installation is priced elsewhere and stays unchanged only if the work is unchanged. The agreement applies the same 20% markup when reconciling the actual purchase cost.

Customer picks a $750 vanity.

  • Purchase difference: $750 − $600 = $150
  • Agreed 20% markup on that difference: $150 × 0.20 = $30
  • Price goes up: $150 + $30 = $180

Customer picks a $500 vanity.

  • Purchase difference: $600 − $500 = $100 in the customer's favor
  • Reverse the 20% markup on that difference: $100 × 0.20 = $20
  • Credit to the customer: $100 + $20 = $120

The $750 selection therefore contributes $900 to the revised price; the $500 selection contributes $600. Compared with the original $720, those are the $180 increase and $120 credit above. This credit reverses markup that was included in the original price; it does not refund money that was never charged.

Notice that the 20% is markup, a percentage added on top of your cost. It isn't margin, which is a percentage of the price you charge. If you write "20%" in an agreement, make clear which one you mean. Here it's markup on the purchase difference.

Avoid double-charging and keep the allowance honest

The biggest fairness risk is charging the allowance and the actual item. The allowance is a placeholder. When the real price is known, it replaces the placeholder. It doesn't sit on top of it.

A few checks keep the line honest:

  • Settle both directions. If the customer picks something cheaper, the money comes back.
  • Show delivery and tax once. They belong either inside the allowance or on their own lines, never both.
  • Keep contingency separate. If a cabinet overage gets paid out of your site-conditions contingency, the customer can't tell what either line was for.
  • Don't call an upgrade an allowance. If the customer wants a feature beyond the scope you priced, treat it as a change to the job.

For changes after the contract is signed, see how to price construction change orders.

Check how your contract defines allowances

Contracts draw the allowance line in different places. AIA's A201 guidance, as explained by AIA Contracts, puts delivered materials and equipment, plus tax, inside the allowance. Labor, installation, overhead and profit go outside it. That's one agreement's approach, not a rule every contract follows.

If you work under a different agreement, match your estimate wording to it. If you want to see how standard documents are organized, the AIA?MBA joint committee contracts page is a place to start. Before you send anything, check that the allowance wording in your estimate matches the allowance wording in your contract.

If the allowance is part of a bigger remodel price, how to bid remodeling jobs covers the rest of that estimate.

A quick checklist before you send the estimate

  • Each allowance line names the item and the quantity or spec you priced.
  • Each line says whether it's material only or installed.
  • Delivery, tax, labor and markup each appear once, and you've said where.
  • The estimate has a selection deadline linked to your ordering time.
  • The settlement method is written for both above and below the amount.
  • Contingency and upgrades sit on their own lines.

Quantities come first. If an allowance is per square foot or per piece, get your counts right before you price it. Organizing material quantities for an estimate shows one way to do that.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors