How to bid remodeling jobs: a worked example
Build a remodeling bid from the work involved. Follow a living-room example, check shared costs and allowances, and turn your figures into a clear customer estimate.

Before you start
- Define what stays, what changes and who handles each part before pricing the work.
- Price purchase quantities, person-hours and subcontractor inclusions, then count shared site costs once.
- Separate confirmed work, selection allowances and unknown repairs so the customer knows what the bid covers.
To bid a remodel, walk the job and write down exactly what's changing. Then price the materials you'll buy, your crew's person-hours, subcontractors and shared site costs. Add markup to cover overhead and profit, and send the total with the scope and assumptions behind it. Below is a worked example for a 12 by 10 ft living room.
Agree a scope you can measure
Square footage alone doesn't make a bid. Two 120 sq ft rooms can need very different prep, access and finish work, so use the walkthrough to define the work before you price it. Write down the answers to these:
- What stays, what comes out and what gets replaced?
- Who supplies the selections, and have they been chosen?
- How do materials and debris get in and out, and which route needs protection?
- Who moves furniture? In the example below, the customer clears movable pieces before you arrive.
- Where does your prep end and the finish trade's work begin?
- Does anything need a return visit, such as paint touch-ups after trim goes in?
- Is any permit or approval needed, and who handles it and pays for it? Confirm this before you give a firm price.
Look at the subfloor, the doorways and the path from truck to room while you're there. If you can't inspect something, say so in the bid rather than guessing.
Price what you'll buy, not what you'll install
Flooring comes in boxes and trim comes in lengths, so you pay for more than the room's measured area. Start with the installed quantity, add the allowance you choose for cuts, then round up to whole packs. Check the pack size of the actual product, and confirm whether the chosen floor needs a separate underlay. Add fixings, thresholds and finishing consumables as their own line so they don't vanish into labor. Our materials-pricing guide shows how to compare purchase quantities, supplier prices and delivery.
If you'd rather not phone around for every line, Construction Job Estimator brings in real-time material prices from local suppliers, including shops you already use. Quantities and costs stay editable, so you can still apply your own cut allowance and pack sizes.
Build labor in person-hours and confirm subcontract scope
A person-hour is one person working for one hour. Two people working four hours is eight person-hours, even though the clock only moved four. Break the job into tasks, assign hours to each, then multiply by the full employment cost of that worker. In the method below, that rate excludes company overhead and profit, which the markup covers. If your own rate already includes either, adjust the markup so you don’t charge it twice. For a fuller method, see our guide to estimating labor costs.
For subcontractors, get the inclusions in writing: which surfaces, what prep, whether paint and protection are included, and whether touch-ups mean a return visit. If the painter's price includes materials and labor, don't add paint or your own painting hours on top.
Count shared site costs once
List shared costs such as delivery, disposal and coordination, then check that each charge appears once. You may need more than one delivery or collection; include every planned visit. Agree who protects the access route and who masks surfaces for painting so you price each task once. In the example below, removal hours cover handling the old carpet, while the disposal line covers the haul and disposal fee. Coordination hours should be specific to this project. Keep general office costs separate from those project hours if your markup already covers them.
Elapsed time works differently. Waiting between visits changes your schedule, but it doesn't automatically add charged person-hours.
Add overhead and profit once
Once your direct job costs are complete, add one markup for overhead and profit. Markup is a percentage added on top of your cost. Margin is the share of the final price that's left over. They aren't the same number: a 25% markup gives a 20% margin before overhead. Don't call the markup amount net profit, because overhead comes out of it first. If you want to test different percentages, the contractor markup calculator does the math.
Worked example: a living-room refresh
The scope is a 12 by 10 ft room, or 120 sq ft. Remove the carpet and existing baseboard and protect the route in. Install a floating floor with its underlay, fit new baseboard and have a subcontractor do minor paint prep and paint the walls, ceiling and new trim. Then clean up. Baseboard runs 44 ft around the room, less one 3 ft doorway, so 41 ft. There are no other floor-level openings affecting this baseboard measurement.
The subfloor is assumed dry, sound and flat to the selected flooring's requirements. There's no structural, layout, plumbing or electrical work.
These are sample USD costs to show the method. Use your own rates and quotes, and add any applicable tax.
| Item | Basis | Sample cost (USD) |
|---|---|---|
| Flooring | 120 sq ft + 10% purchase allowance = 132 sq ft; 20 sq ft boxes, so 7 boxes (140 sq ft) × $55 | 385 |
| Underlay | 7 packs of 20 sq ft × $9 | 63 |
| Baseboard | 41 ft × 1.10 = 45.1 ft; 8 ft lengths, so 6 lengths (48 ft) × $18 | 108 |
| Fixings, threshold, finishing consumables | Sample supply cost | 75 |
| Own labor | 29 person-hours × $45 | 1,305 |
| Painter (subcontract) | Agreed minor prep, labor, paint; walls, ceiling, new baseboard | 760 |
| Delivery | One combined charge | 80 |
| Disposal | Haul and disposal fee | 140 |
| Direct job cost | 2,916 | |
| Markup | 25% of direct cost, for overhead and profit | 729 |
| Price before tax | 3,645 |
Here's how the 29 person-hours break down:
- Protection: 4
- Removal: 6
- Flooring installation: 10
- Baseboard: 4
- Cleanup: 3
- Job coordination: 2
The $45 rate includes employment costs but excludes company overhead and profit. These hours, the 10% purchase allowance and the 25% markup are sample choices; set yours from the job and your business costs. Check the baseboard cutting layout before buying: rounding to six lengths alone doesn’t prove every cut will fit. The painter’s sample price includes paint and painting labor, so neither is added again.
Compare supplier and subcontractor quotes like for like
Before you trust a number, check what it covers. For a supplier quote, confirm the exact product, the pack size, whether tax is included, the delivery charge and how long the price holds. For the painter, confirm the surfaces, prep, materials, protection and any return visits. Then compare against your own lines for overlaps, such as protection or disposal showing up twice.
Handle selections and unknown conditions
A selection allowance and an uninspected repair are different things, so write them differently. If the customer hasn't picked the floor, don't put down one unqualified number. State the scope and quantity, what the allowance covers, the pack and waste assumptions and how any difference will be priced.
For example, if the customer swaps the $55 box for a $65 box and you still need the same 7 boxes, that adds $70 in direct cost. With the same 25% markup, that's $87.50 before tax, assuming the prep and install stay the same. Agree how selection changes affect the price before the customer chooses the replacement. A different floor may need a different underlay or more labor, so reprice all the affected work. In Construction Job Estimator, you can edit the box price in your estimate and review the new total before you go back to the customer.
Hidden subfloor problems are a separate matter. The flooring purchase allowance covers cuts, not repairs. For this sample bid, significant leveling and damage repairs are excluded. If you uncover a problem, assess the repair and agree its price and effect on the schedule before carrying out that additional work. Keep the agreed change in writing. NAHB’s selection allowance and change order forms provide separate places to record selections and changes to scope, price and completion.
If the remodel includes exterior cladding, our siding bidding guide shows how to price removal, panels, trim and access before adding overhead and profit.
If your remodel starts with a strip-out, our interior demolition pricing guide covers protection, removal labor, debris volume and disposal costs.
What to send your customer
For a fixed-price bid, your customer needs a clear scope, price and assumptions. Your internal worksheet can hold the detailed cost rates and markup; include a cost breakdown if that’s part of your agreement. Send a document that covers:
- Specific scope and product specs, or clear allowances where selections are open
- Price, with tax shown clearly
- Exclusions and assumptions
- Who is responsible for what
- A time window that depends on selections and access
- Payment terms and how long the price is valid, based on how you actually run your business
- How changes get agreed
Check that supplier quotes haven't expired before you commit to a firm price. For the example, the scope could read:
Remove carpet and existing baseboard in 12 × 10 ft living room. Supply and install customer-selected floating floor with approved underlay, new baseboard, minor paint prep and paint to walls, ceiling and new baseboard. Existing subfloor assumed dry, sound and flat to flooring requirements; leveling or damage repair priced separately if found. Customer clears movable furniture before arrival. Total $3,645 before applicable tax.
Add the selected product details, agreed terms and responsibilities before sending. For layouts, see our remodeling estimate template and construction estimate example.
You can also start from the walkthrough itself. Describe the job to Construction Job Estimator by voice or text, add site photos, and it turns those details into a working estimate. Materials, labor and other costs sit in the same estimate, and you can see the quantities, prices and labor behind each figure and adjust them. From there you can prepare a professional estimate or quote for your customer in minutes, and convert it to an invoice once it's accepted. You still set the scope, exclusions and markup. The remodeling estimating app page covers how it handles remodels.