How to Bid on Commercial Electrical Jobs

Price the full electrical scope, check what supplier packages and labor units include, and send a bid that matches the job.

3D electrical contractor reviewing lighting plans in an unfinished office beside boxed fixtures and cable reels

Before you start

  • Check the specifications and other trades� schedules as well as the electrical plans.
  • Price complete assemblies and verify what labor allowances already include.
  • Separate project costs, company overhead and markup before submitting your bid.

Read the whole bid package first. Then settle who supplies and connects each system, take off by assembly, get matching supplier packages, build labor from your own units, and price the job conditions. Last, check that your submission matches what the GC asked for. That order protects you from missed scope, underpriced labor, and a bid the GC can't line up against the others.

This guide assumes you already know basic electrical estimating. If you want the fundamentals of pricing electrical work, start with how to estimate electrical work. What follows is the commercial sequence on top of that.

Read the full bid package before you count anything

Start with the latest bid instructions, drawings, specifications, addenda, and the equipment and lighting schedules. Write down the revision dates and the deadline. A bid built on a superseded sheet is a bid you'll have to defend later.

The drawings don't tell the whole story. NECA's article on specifiers describes the specification as the document that covers products and performance, administrative submittals, and execution and testing, alongside the drawings (NECA). In practice, that means testing, closeout paperwork and submittal obligations can sit in the spec and never show on a floor plan. Read those sections for work you'll have to price.

Then cross-check the sheets against each other. Compare the lighting plans, power plans and panel schedules. After that, look at the mechanical, equipment and architectural sheets that touch your work. Equipment that appears on one sheet and not another is a common source of missed connections.

When sheets conflict, ask the design or GC contact in writing, and keep the answer in the bid file. Don't settle it by guessing. The same goes for unclear routing or design intent. Confirm the design requirements with the responsible designer before pricing them.

Write down who supplies and connects each system

Scope can be missed where trades meet. A simple responsibility list helps you check those gaps before you price. For each item, record who supplies it, who installs it and who makes the final connection:

  • Distribution equipment
  • Lighting and controls
  • Power
  • Equipment connections
  • Fire alarm, data, security and BAS interfaces
  • Demolition
  • Temporary power
  • Utility work, trenching and backfill
  • Penetrations and firestopping

Resolve each boundary instead of assuming a system is in or out. If the fire alarm contractor supplies the devices and you run the conduit, that needs to be written down somewhere you can both point to. Then carry the agreed responsibilities into your bid, so the GC sees the same split you priced.

A quiet exclusion doesn't take out scope the documents require. If you think something shouldn't be in your price, raise it through the bid process and get it clarified.

Also keep two kinds of items apart. An excluded item is unpriced and says so. An allowance carries a stated amount that sits in your number. If you blur the two, the GC can't compare your bid fairly.

Take off by assembly and by the actual route

Count specified equipment and devices by type. Measure cable, conductors and raceway by the specified size and type, along the real route, including rises and drops. A plan-view length misses every vertical run.

Then add what ties it together: supports, boxes, fittings and terminations. The cleanest way to avoid gaps is to count by assembly. Decide what each assembly contains, count the assembly once, and check that its fittings and labor aren't also showing up as separate lines.

Keep quantities in a form you can trace. When an addendum moves a panel or adds a run, you want to find the affected lines fast and change only those. The electrical estimate template gives you a layout for organizing the takeoff and cost lines together.

Compare supplier packages like for like

Get matching quotes for the lighting package, controls, distribution equipment and any specialist work that applies. Then compare what's actually in each one:

  • Bill of materials
  • Commissioning or startup included
  • Accessories
  • Freight
  • Tax basis
  • Delivery date
  • Quote validity
  • Substitution approval

A low quote that leaves out required controls or startup isn't cheap. It's incomplete, and the missing piece lands in your cost later. Check delivery dates and validity against your own schedule, and confirm any substitution has been approved before you price it.

Once you've read the package and settled scope, Construction Job Estimator helps you gather the numbers. You can pull real-time material prices from local suppliers, compare supplier options, choose your own supplier, or enter a price you already have, such as a written quote for a lighting package. Bring those prices together with your labor and other job costs, then review the breakdown and prepare a professional estimate or quote in minutes.

Check what your labor allowances include

Labor is your quantity times your own tested labor unit, plus allowances for job-specific conditions. Before you multiply, check two things: the unit basis (each or per 100 feet) and what work the unit already covers.

Published labor units are a useful example of why this matters. The NECA Manual of Labor Units public overview says its units include normal handling, drawing study, measurement and layout, installation and normal nonproductive labor, and that they exclude supervision. It also notes that conditions vary (NECA). You may use your own units rather than NECA's, but the question is the same: what's already inside the number? If handling and layout are in the unit, adding them again double counts them. If supervision is outside, someone has to price it.

For job conditions, add reasoned tasks you can name, such as extra setup for a second floor. If you apply a productivity adjustment, record what it covers and why it fits this job. Check that you have not also added the same extra hours separately. Keep supervision as its own line so it's neither missed nor counted twice.

In Construction Job Estimator, you can see and edit labor time and rates next to materials and other job costs, so a change to hours shows up in the same estimate as the material lines.

Price commercial conditions as real paid hours

Check the conditions on this commercial project and price what applies:

  • Height and access equipment
  • Occupied areas
  • Phased work
  • Restricted deliveries
  • Other trades working in the same space
  • Approved shutdown windows
  • Repeated setup
  • Controls commissioning
  • Inspection or test attendance
  • Labeling, as-builts and handover
  • Project supervision

Price the hours people are actually paid, plus any overtime or standby you've agreed to. Elapsed time and paid hours aren't the same. If a phase spans three weeks but two electricians each work 40 hours on it, that is 80 person-hours. Add any actual paid standby or return visits separately if they are not already included. Keep person-hours separate from elapsed job time in your notes so the schedule and the cost don't get mixed up.

Keep equipment hire, delivery and specialist startup as other direct costs. Hiding them in labor makes the labor look off and makes the bid harder to review. Include the costs of project-specific access and safe working arrangements in the appropriate lines.

Example cost summary for a small office fit-out

These hypothetical USD costs and hours illustrate a small, unoccupied office fit-out. They are not supplier quotes, NECA labor units or a market rate; use your own project costs.

The scope covers lighting and controls, receptacle circuits and specified equipment connections from existing distribution. There's no service upgrade, and the design team confirms the existing supply is suitable. Data and fire alarm are installed by agreed specialists, and the interfaces are allocated in the scope matrix.

Line USD
Materials 12,500.00
Labor 9,984.00
Other direct costs 1,800.00
Direct cost 24,284.00
Company overhead 2,000.00
Total cost 26,284.00
Markup, 20% of cost 5,256.80
Bid before tax 31,540.80

The labor total is 208 person-hours � $48 = $9,984. The hours break down like this:

Task Person-hours
Raceway and wiring 120
Fixtures, devices and controls 56
Testing, labeling and handover 16
Project supervision and coordination 16
Total 208

Other direct costs are a $900 lift rental, $200 delivery and $700 for specialist controls startup. That startup is separate from the electrician's own testing and coordination hours, so it isn't counted twice.

Three details matter. The hours already include handling, layout and setup for this project, so there's no extra line for them. The $48 an hour is wages and employment cost only. Supervision sits inside the 16 hours, and company overhead is added once, separately.

Also notice that a 20% markup on cost isn't a 20% margin. The $5,256.80 markup is about 16.7% of the $31,540.80 bid. The 20% markup is an example choice, not a recommended rate. The contractor markup calculator lets you check the difference for your own numbers.

Check the bid before sending

Run through these before you submit.

  • Count overhead once. If your labor rate is already a billing rate that includes overhead or profit, don't add them again on top.
  • Match what was asked. Include the base bid, alternates, unit prices if requested, the addenda you received, conditions, validity period, schedule and tax treatment, in the form the instructions call for.
  • Check the project's requirements. Look at the actual insurance or bond requirements, and add your own costs for them only where the project calls for them. They vary by project.
  • Make the scope read the same everywhere. Your scope matrix, exclusions and allowances should say the same thing in the bid as in your estimate. That's what lets the GC compare you fairly.

Before sending, check for any last-minute addenda and confirm that the final total matches the scope and alternatives you are submitting. Save the exact version you sent so later changes have a clear starting point.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors