How to estimate an electrical job: scope, labour and price
Price the work around the fixture count, including access, shutdowns, testing and the costs that are easy to leave out.

Before you start
- Confirm the fixture specification, existing conditions and access before pricing.
- Include setup, testing and return visits in your labour allowance.
- Check that your selling rates recover overhead and profit once.
To estimate an electrical job, start with the scope and site conditions, then price materials, labour and other job costs. Add enough to cover overhead and profit before you send the estimate. The fixture count matters, but so do the hours around it: access, shutdowns, testing and cleanup.
How residential electrical work differs from the office example
Price a home from what you assess on site or read from the current plans, not from a device count. The office example had eight fixtures at existing positions. A home job often has no such fixed starting point.
In an occupied home, the existing circuits and equipment decide the scope. Assess them and write down your assumptions, as the office example does. For a new build or rewire, list the circuits and equipment you're pricing and the ones you aren't.
A device count misses route length and access. Eight outlets might mean short runs in one house and long runs through finished walls or an attic in another.
Price route, access and making good as tasks
Give route planning, working through tight or finished spaces, and moving and protecting your customer's belongings their own person-hours. Don't hide them in a per-device allowance.
Say who makes good after you open finishes: you, your customer or another trade. If it's you, price the time and materials. If it isn't, list it as an exclusion so your customer knows before they accept.
Add testing and documentation as separate hours, along with any return visit you expect. Check the actual permit and inspection requirements for the job with your local authority. Confirm who is responsible, and price the fees and attendance you must cover. An exclusion in your quote doesn't remove a legal obligation.
Supplier costs, overhead and profit then go on as explained earlier. Written this way, your quote shows the scope, assumptions, exclusions and price, so your customer can see what the price covers.
Worked example: replacing eight office light fixtures
The job is to replace eight customer-approved light fixtures at their existing positions in an accessible office. There are no new circuits, no panel changes, no rewiring and no repairs to the building. The example assumes suitable existing circuits and controls. Confirm that during your site assessment before offering this scope.
These are sample prices in USD; use your own costs for your job.
| Item | Basis | Your cost (USD) |
|---|---|---|
| Fixtures | 8 × $75 | 600.00 |
| Fixings, connectors, consumables | 1 allowance | 60.00 |
| Access equipment hire, including delivery and collection | 1 job | 150.00 |
| Disposal fees | 1 job | 40.00 |
| Labour | 16 person-hours × $45 | 720.00 |
| Direct cost | 1,570.00 | |
| Allocated overhead | 160.00 | |
| Cost base | 1,730.00 | |
| Markup | 25% of cost base | 432.50 |
| Price before applicable tax | 2,162.50 |
The $45 hourly labour cost includes wages and employer costs. It is the cost to your business, before overhead and profit, rather than the rate you charge your customer.
What your scope needs to say before you price
Eight fixtures in an empty office and eight above occupied desks can need different labour allowances. If you can only work in short shutdown windows, you may have to set up and pack down several times. Find that out before you settle on a price.
Before you price, settle the points that change your hours and your job costs:
- Which fixture is going in. Check that the specified fixture suits the mounting and the existing controls. A fixture that doesn't fit means a return trip or a different part.
- What you're assuming about the existing circuits and controls. Check suitability before committing to the replacement scope. If further investigation is needed, make that clear and agree how any repairs will be priced.
- Ceiling height and access. This decides whether you need access equipment and how long setup takes.
- When you can work. An occupied office may give you a limited shutdown window, which can force staging or after-hours work.
- Who owns the old fixtures. Confirm whether you will leave them with the customer or arrange disposal. Allow time for handling either way, and obtain a disposal or recycling price if you are taking them away.
- What's excluded. Name any work outside your price, such as new circuits, panel changes or ceiling repairs. Confirm who is responsible for permit and inspection arrangements.
Count the job before you price the hours
On a job this size, the takeoff is a list you can check on site: fixture count, fixture type, ceiling heights and what you'll need to get to them. Make the fixtures their own line. Keep fixings, connectors and consumables in a separate allowance so a small consumables overrun doesn't hide inside the fixture price.
This is also where hand-pricing slows you down, because every fixture and fitting needs a current price. Construction Job Estimator lets you describe the job by voice or text and add photos of the ceiling and existing fixtures. It then builds a working estimate with real-time material prices from local suppliers. Materials, labour and other job costs sit in one estimate. You can open any line to check the quantity and price, and change it to match your own costs.
Larger jobs run off plans, and that's a different process. You work from the current drawing and spec revisions and count devices and fixtures separately from measured cable and conduit routes. You record heights, routes and allowances, and you reconcile any subcontract quotes against your own scope. There's no universal per-square-foot rate that replaces that work. This example covers a small replacement job; a larger tender also needs that drawing and specification review.
Two job costs deserve their own lines even when they're small:
- Access equipment. The $150 in the sample is one job price that already includes delivery and collection, so don't add a separate delivery charge. If the work is staged, check whether the hire period, delivery charge or setup time changes.
- Disposal. Keep it apart from the removal labour. Removing a fixture is time on the clock. Disposal is a separate charge. Record whether your price includes it.
Build labour from tasks, not from fixture count
Break the 16 person-hours into the tasks you'll actually do.
| Task | Person-hours |
|---|---|
| Preparation, access setup and shutdown coordination | 3 |
| Fixture removal and replacement | 8 |
| Testing and documentation | 3 |
| Cleanup and loading | 2 |
| Total | 16 |
Use hours that fit your crew, access and testing requirements. A second visit needs its own travel and setup time; check that those hours are in your allowance.
Person-hours are hours worked, added across everyone on the job. Two people for eight hours and one person for sixteen both come to 16, but they're not the same job on site. Your shutdown window and any equipment hire follow the clock, so check elapsed time separately.
Build the allowance around the people who can do each task. If an electrician and a helper have different costs, calculate their hours separately before combining them. Include your own working time too. You can check the totals with the material and labour cost calculator.
Use your own history first
Compare the hours you allowed on previous jobs with the hours your crew actually used. Record why a job took longer: difficult access and a missed testing visit need different adjustments next time. If you also use a published labour-unit reference, read what tasks each unit includes and adjust for the conditions on your job. The NECA Manual of Labor Units is an experience-based electrical estimating reference with separate units for normal, difficult and very difficult installation conditions.
Add overhead and markup once
In the sample, the $160 of allocated overhead sits on top of $1,570 of direct cost, which gives a cost base of $1,730. Markup is then 25% of that cost base: $432.50.
Choose an overhead allowance that reflects your business costs and realistic billable hours. Keep expenses already included in your direct labour cost out of that allowance. If you add it to your labour rate and then add it again as a line, you've charged for it twice. The same goes for profit. If your selling rates already carry markup, don't apply markup to the total as well.
Also keep markup and margin apart. A 25% markup on cost gives a 20% margin on this price, because $432.50 is 20% of $2,162.50. If you wanted a 25% margin, you'd need a markup of about 33.3% on cost. The contractor markup calculator will convert between the two.
Turn your costs into the price you send
Your customer needs to see what you will supply and do, and what it will cost. You can keep your internal costs separate. In this example, the labour selling rate includes the overhead: $720 of labour plus $160 of overhead is $880. Spread over 16 hours, that's $55 an hour, and 25% markup brings it to $68.75. Every other direct cost carries the same 25%.
| Line | Quantity | Rate (USD) | Amount (USD) |
|---|---|---|---|
| Fixtures | 8 | 93.75 | 750.00 |
| Fixings, connectors, consumables | 1 | 75.00 | 75.00 |
| Preparation and replacement | 11 h | 68.75 | 756.25 |
| Testing and documentation | 3 h | 68.75 | 206.25 |
| Cleanup and loading | 2 h | 68.75 | 137.50 |
| Access equipment | 1 | 187.50 | 187.50 |
| Disposal | 1 | 50.00 | 50.00 |
| Total before applicable tax | 2,162.50 |
Preparation and replacement is 11 hours because it combines the 3 hours of preparation with the 8 hours of removal and replacement. The electrical estimate template uses these same selling rows. Because the rates already include markup, the worksheet adds none on top.
Show applicable tax separately, using the correct treatment for the job. Canadian contractors can use the same method with their own CAD supplier quotes and labour costs. Changing a currency label does not convert the sample prices.
Settle the unknowns before you commit the price
Before sending it, check the customer and project details, fixture specification, validity and payment arrangements. Resolve the remaining questions that could change your price or start date:
- Permits and inspections. Check what's required for the actual job, including any third-party inspections and fees, before you commit. The sample excludes authority fees and unplanned remedial work. Confirm the requirements and price any required items separately before issuing your final estimate.
- Existing conditions. If your assessment shows the circuits or controls aren't suitable, that's outside this price. Talk it through with your customer and agree a revised price before any extra work starts.
- Supply. Get the fixture availability and quoted lead time from your supplier before you promise a date. A long lead time can push your work out of the shutdown window you planned around.
- Return visits. If you expect a second trip for testing or documentation, decide whether it's in your hours or not, and tell your customer which.
Send the estimate, then bill the job
Once your scope, exclusions and hours are settled, Construction Job Estimator can prepare the professional estimate or quote you send your customer. If they accept, you can convert that estimate into an invoice, so the figures you agreed carry through to billing.
Choosing an app for this work? Compare electrical estimating software for small contractors for site-visit quotes, drawing takeoffs and detailed electrical bids.
Preparing a bid for a general contractor? See how to bid on commercial electrical jobs for scope responsibilities, supplier packages and labor allowances.
For a complete cost breakdown and matching customer document, explore this electrical estimate example.