How to Bid on a Commercial Painting Job

Price the specified finishes and the conditions you will work in, then submit a bid that makes your scope, assumptions and costs clear.

3D painting contractor reviewing room plans in an office reception beside paint swatches and protected furniture

Before you start

  • Check drawings, finish schedules and revisions before pricing the scope.
  • Include phased access, repeated setup and coordination in your labor allowance.
  • Submit the required bid breakdown with clear scope and separately priced alternatives.

Collect the latest bid documents, settle any scope conflicts in writing, and measure by surface and specified paint system. Then price the labor that access rules create, add overhead and markup, and submit exactly the way the bid form asks. Commercial bids differ from house estimates mostly in the paperwork, the specified finishes, and the restrictions on when and where you can work.

Start with the latest bid documents

Before you price anything, gather the invitation or instructions, drawings, finish schedule, paint specifications, and addenda. Addenda are the issued changes to the original package. Write the revision and date on each document so you know what your number is based on.

Next, pull the logistics from the instructions: the deadline, how to submit, any breakdown they want, alternates, whether there's a site visit, and the cutoff for questions. Check whether the form asks for a base price, separately priced alternatives, or acknowledgment of issued changes. Follow the form in front of you.

A manufacturer's commercial spec guide can show how finish schedules usually split by room use, substrate, coating system, and sheen. Treat that as a pattern for organizing your own takeoff. Your job's specification is what counts.

Settle scope conflicts in writing before you price

Drawings, finish schedule, and specs don't always agree. Maybe the schedule calls for a two-coat system in corridors while the spec section lists something different. Ask the GC or facility contact in writing before you price, and keep the answer.

Don't assume an exclusion in your own notes overrides scope the documents make mandatory. If the documents require something you'd rather leave out, ask about it. Don't quietly price around it.

If there's a site visit, use it. Look at substrate condition, ceiling heights, access routes, and existing coatings. Record what you saw and get any change to the required scope confirmed in writing.

Build the takeoff by room, surface, and system

Give every line in your takeoff the same fields: location, substrate, paintable quantity, prep, primer, topcoat, sheen, color, number of coats, and a drawing or schedule reference. Keep wall area, ceiling area, and door or frame counts separate. Floor area is not wall area, and mixing them is an easy way to misprice a room.

Price the specified system, not the cheapest generic paint. If you want to offer a substitute, it has to go through the approval route the documents set out.

Prep depends on substrate, environment, and surface condition. Sherwin-Williams' surface preparation guidance notes that previously coated surfaces need prep and, where needed, a compatible primer. Coverage also varies with application method and surface, so check the selected product's data sheet instead of relying on a rule of thumb. Round each distinct product and color separately, because a gallon of wall color can't cover a shortfall in door paint. The paint calculator is handy for quick quantity checks, and the painting estimate guide covers the basic room-by-room math.

Price the labor that commercial access creates

Square footage doesn't capture most of the extra time on commercial work. Look for these conditions in your documents and on site:

  • Occupied spaces and phased room release
  • Repeated protection and setup in each phase
  • Short work windows and escorted access
  • Storage and delivery limits
  • Ceiling height and access equipment
  • Noise or odor restrictions
  • Other trades working in the same areas, and touch-ups after them

Ask who moves furniture and which areas have to return to service, and by when. Those answers change how many times you set up and how long each setup takes.

Price the time your crew is actually paid. Overnight drying isn't automatically paid labor. Allow for any paid waiting, monitoring or return visits the job actually requires. Product data and site conditions decide when a space is ready, so don't promise a universal reopening time.

Show hours per task, including supervision, site coordination, and samples or paperwork if the job requires them. Keep job direct costs (labor, materials, equipment, delivery, disposal) separate from company overhead, so overhead gets counted once.

Check any insurance or bond requirements before committing your price. Also check when you will be paid and whether any payment will be held back until completion. Allow for your confirmed costs rather than copying a percentage from another job.

Bring your costs into one estimate

By this point you have measured quantities, a specified system, and hours by task. Construction Job Estimator is useful for turning those notes into costs. You can describe the job by voice or text, include the measurements you took, and add site photos to build a working estimate. It pulls real-time material prices from local suppliers, and labor, delivery, equipment hire, and disposal go into the same estimate.

You stay in control of the numbers. You can review and change quantities, products, labor time and rates, markup, and individual line items. Then the app prepares a professional estimate or quote in minutes. You still choose the specified products and enter your measured quantities. You also check the result against the bid form, because the form is what you submit.

Example: a two-phase office repaint

This is a small sample to show how phasing, other costs, overhead, and markup shape the final number. These are sample prices in USD, and the coverage rates and hours are made up for teaching; use your own costs for your job.

Scope: An occupied office suite is repainted in two agreed room-release phases during normal daytime work. The client clears each released zone, and you protect the remaining fixtures and floor.

The job has 3,600 sq ft of net painted drywall wall area and 12 existing door and frame sets, measured at 600 sq ft across both faces and frames. It uses one wall color, one door color, and two specified finish coats. About 200 sq ft of minor wall patches need spot primer, and existing coatings were assessed as compatible.

Ceilings, exterior work, wallcovering removal, major board repair, and hazardous coating work are excluded. The base price has no after-hours premium.

Materials assume 350 sq ft per gallon for finish, 300 sq ft per gallon for primer, and a 10% allowance. For walls, that's 3,600 × 2 coats ÷ 350 × 1.10, or about 22.6 gallons, so you buy 23.

Item Basis Amount (USD)
Wall paint 23 gal at $48 1,104.00
Spot primer 1 gal at $32 32.00
Door and frame paint 4 gal at $65 260.00
Sundries Tape, plastic, rollers 220.00
Materials 1,616.00
Labor 132 hours at $36 4,752.00
Access equipment 300.00
Delivery 100.00
Waste fee 90.00
Direct cost 6,858.00
Company overhead 650.00
Total cost 7,508.00
Markup 20% of cost 1,501.60
Bid before tax 9,009.60

The 132 person-hours break down like this: 20 for phase protection and repeated setup, 24 for cleaning and minor prep, 4 for spot primer, 40 for wall coats, 24 for door and frame coats, 12 for cleanup, and 8 for coordination, samples, and the punch list. The $36 hourly figure covers wages and employment costs only, with no overhead or profit in it. Setup for both phases is already inside those 20 hours, so don't add it again.

The 20% is a sample choice, not a standard. It's markup on cost, which is different from margin. Here the $1,501.60 is 20% of the $7,508 cost but about 16.7% of the $9,009.60 bid. The contractor markup calculator shows the two side by side.

Don't divide the whole bid by the 3,600 sq ft of wall area to get a per-foot number. The bid also covers doors, frames, and the cost of two phases, so the result would mislead you on the next job. And if the owner moves the work window to after hours, price that change explicitly. Don't assume a standard premium.

Put the bid together and submit it

Build the bid in the structure the form asks for. That usually means the base price, references to the documents and revisions you priced from, and your phase and access assumptions. Add any required alternates, separately priced options, and approved clarifications. Handle tax the way the form says to. Don't leave out scope the documents require, and don't override tax instructions on the form.

Confirm the validity period, duration, and payment conditions they request. Raise any terms you cannot meet before the deadline for questions. If the form asks you to acknowledge addenda, do it. Then submit the correct form or files by the stated route, and confirm that they were received.

Before sending, check that your price still matches the latest scope and the agreed access conditions. A change to either can undo careful estimating if it never reaches your final bid.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors