How to price an exterior house-painting job

Build an exterior painting quote from the surfaces and conditions in front of you, with a worked example covering prep, paint, crew time and access.

3D painting contractor assessing a house exterior with color swatches, a phone and neatly arranged paint supplies

Before you start

  • Measure paintable wall faces and gables rather than house floor area.
  • Cost preparation, protection and access alongside paint and person-hours.
  • Add overhead and profit once, then explain exactly what your quote includes.

To charge for an exterior house-painting job, measure the surfaces you'll actually paint. Cost the preparation, materials, labor, access and other expenses, then add your overhead and the profit you want. Finally, write down exactly what's included. Use a price per square foot to check the result, rather than choosing a rate before you've assessed the work.

If you'd rather not build every estimate line by hand, describe the job to Construction Job Estimator by voice or text, with your measurements and photos. It brings real-time local supplier material prices, labor and other costs into a working estimate you can review and turn into a professional quote in minutes. Here's how to work out the scope and figures behind it.

Measure the surfaces you will paint

House floor area isn't exterior wall area, so measure each elevation. For a rectangular face, multiply width by height. For a gable, treat it as a triangle: base times height, divided by two. Then deduct the openings you won't paint, such as windows and doors, and deduct them the same way on every elevation.

Price the work around those openings separately. Protecting a window and cutting in around it takes time even though the glass isn't paint area.

Keep separate lines for each of these:

  • Walls and siding
  • Gables
  • Trim, fascia and soffits
  • Doors and windows themselves
  • Decks and fences
  • Detached structures

If your customer drops the fence or adds the trim, you change one line instead of redoing the whole price. When you have the net area, the paint calculator handles the step from area to gallons. Measure from the ground or from a safe position, and plan access around what you find on site.

Price the preparation and access

Walk every elevation before you price it, and write down what you see. Note the existing coating, the substrate and its texture, peeling areas and repairs, and any color or coat-count change. Also record plants or other things that need protection, plus height, roof slope, reach and masking.

Then turn those notes into tasks and person-hours. Cleaning, minor prep, masking, spot priming, finish coats and cleanup each get their own hours. A blanket "prep is 20% of the job" hides the difference between a clean, sound wall and a flaking one.

Person-hours are the hours each worker is paid. Two people working a full eight-hour day add up to 16 person-hours, however many calendar days the job takes. Keep those two ideas apart.

Choose the coating system for each surface before counting gallons. Siding, trim and bare patches may need different products; Sherwin-Williams' exterior guidance covers those preparation and product choices. Include any required primer in both your materials and your labor.

Resolve problems before fixing the price

Some findings change the scope, not just the hours. Rot, moisture that hasn't been resolved, or a coating you suspect is hazardous all need an assessment first. Settle that scope with your customer before you give a firm price for ordinary painting. Writing "excluded" on the quote doesn't replace finding out what you're dealing with.

On coatings, the EPA warns that disturbing lead-containing paint can create hazardous dust. If you suspect it, establish the coating's condition and get a qualified assessment before you price ordinary sanding or scraping. Check the rules that apply where you work.

The example below assumes the site assessment confirmed that ordinary preparation is suitable.

Example: an exterior repaint

These are sample prices in USD. The costs, hours and coverage figures are teaching inputs, so use your own costs and the coating's technical data sheet for your job.

Scope: an accessible single-story house with wood siding wall faces only. It gets one color and two finish coats. The assessment confirmed ordinary prep is suitable, and 120 sq ft of bare patches get a compatible spot primer. Trim, fascia, soffits, the doors and windows themselves, decks and detached structures aren't painted, though they're protected as needed. Rotten-board replacement and hazardous-coating work aren't included.

Area

Surface Calculation Sq ft
Walls 160 ft × 10 ft 1,600
Two gables 20 × 10 ÷ 2, twice 200
Openings deduct −240
Net paintable 1,560

Paint: 1,560 sq ft × 2 coats ÷ 350 sq ft per US gallon × 1.10 allowance is 9.81 gallons. Buy 10 one-gallon cans at $55, which is $550. The 10% allowance is a sample figure, not a rule. The spot-primer calculation is 120 sq ft � 300 sq ft per US gallon = 0.4 gallon. Buy one US gallon at $30. Consumables such as tape, plastic and sundries are $120.

Labor

Task Person-hours
Cleaning 8
Minor preparation 16
Protection and masking 8
Spot priming 4
Two finish coats 24
Cleanup and handover 4
Total 64

At a loaded cost of $32 an hour, that's $2,048. The $32 covers wages and employment costs only, with no company overhead and no profit. Two workers at 32 hours each is four 8-hour days apiece if both are fully engaged.

Other costs are $240 for access equipment, $60 for the waste fee and $80 for travel and vehicle.

Item USD
Materials 700
Labor 2,048
Access, waste and travel 380
Direct cost 3,128

Add overhead and profit

Add your allocated company overhead once. In the example it's $320, which brings the cost to $3,448. Overhead isn't hidden in the labor rate here, so it isn't counted twice. If you already recover some overhead through your hourly rate, add only the overhead not covered there.

Next comes markup, meaning a percentage added on top of your cost. A 25% markup on $3,448 is $862, so the price before tax is $4,310. The 25% is a sample business choice, not an industry standard. Pick your own, and the contractor markup calculator can help.

Markup and margin aren't the same number. That $862 is 25% of cost but 20% of the $4,310 price. It's what's left after direct costs and allocated overhead, not a guaranteed net profit. Any company costs you haven't allocated still come out of it.

Here's how extra time changes the price. Eight more person-hours at $32 adds $256 in direct cost. With overhead unchanged, that's $256 × 1.25 = $320 more on the price, which makes it $4,630.

Allow for drying and weather

Take coverage, primer, number of coats, recoat timing and weather limits from the coating's technical data. Sherwin-Williams' exterior application FAQ makes the point that suitability depends on temperature and moisture beyond the moment of application. The product guidance governs, so don't carry a drying time from one product to the next.

Drying and weather delays stretch your calendar, but they aren't automatically paid person-hours. The four working days in the example are not a completion promise. If you expect a paid return trip, or you'll hire equipment for longer, put it on the estimate as its own line. Don't add a vague weather surcharge.

Check the price and write the quote

Divide $4,310 by 1,560 sq ft and you get about $2.76 per sq ft of net paintable wall area. That's an output of this example, not a market rate. Compare your own total against past jobs of similar scope. If it looks off, recheck your measurements, hours and exclusions instead of nudging the price toward a rate.

Your customer should be able to read exactly what they're buying. For the example, the quote says:

  • Included: wall and gable siding, protection, spot priming of bare patches, and two finish coats in one color.
  • Not painted: trim, fascia, soffits, the doors and windows themselves, decks and detached structures.
  • Not included: rotten-board replacement and hazardous-coating work.

State any applicable tax separately from the $4,310. For a ready layout, use the painting estimate template. For interior jobs and the general approach, see the painting job estimating guide.

Once your measurements and site notes are in hand, Construction Job Estimator builds the estimate lines for you to review. You check the quantities, labor time, rates and markup, then send a professional quote.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors