Print and fill it in
A clean, one-page worksheet with task-specific line items and space for scope, exclusions and payment notes.
Download blank PDF Get the completed exampleA clear price. A professional first impression.
Download a blank garage conversion estimate to print, a completed PDF, or an editable Excel file. The sample prices a 240 sq ft garage fitted out as an office to an agreed specification, so you can see the scope, exclusions and allowance before you adapt it.
PDF & Excel · No signup for templates · By Daniel
Prepared for: Sample customer
Scope and exclusions included in the download.
Choose your starting point
Download it now, add your business details and make the numbers your own.
A clean, one-page worksheet with task-specific line items and space for scope, exclusions and payment notes.
Download blank PDF Get the completed exampleEnter your quantities and selling rates. Line amounts, selected-line tax and the total calculate for you.
Download ExcelIncludes a blank template and a completed example.
The details that make it clear
Set out the assessed size, intended use and specification, then show what each priced package includes. Keep exclusions and provisional allowances visible beside the scope. Use the printed PDF for handwritten estimates or the Excel workbook for editable descriptions and formula totals. A separate browser editor is also available on this page.
Confirm the measurements and the design your packages follow. The sample's 240 sq ft floor and ceiling quantities come from a 12 by 20 ft assessed space. Replace them with your own measured figures.
Say what each package supplies, installs and finishes. A row like wall insulation and lining should tell the customer exactly what the price covers, so nobody assumes extra work is included.
List what the price leaves out. The sample excludes design, permit fees, structural strengthening, bathroom, kitchen, utility upgrades and concealed defects. Put that list on the estimate itself, not in a separate email.
Label provisional figures, like the heating row, so the customer knows they may change. Add a note on when you'll confirm the amount and how you'll revise the estimate if it moves.
Say how many outlets and lights you're pricing and where they go. The sample covers four outlets and three lights, with installation and testing, and no service upgrade.
Check each row's quantity times rate and the final sum. Make sure overhead and profit appear only once, and show applicable tax as its own line after the subtotal.
From site visit to a clear figure
Start with the assessed size, the intended use and the design you're pricing to. Write it as one scope sentence at the top. Every row below should trace back to that sentence.
Price each row from your job costs and the person-hours you expect to spend. To build this faster, Construction Job Estimator lets you describe the job by voice or text, enter your measurements and add site photos. You then review quantities, labor time, rates, markup and line items before sending a professional estimate or quote.
Edit the eight Excel row descriptions and the scope and exclusions notes to match the work. If you need more line items, use the separate browser editor. Describe what each package includes so extra work does not disappear inside a short label.
Flag anything provisional, such as heating, and say when you'll confirm it. Keep applicable tax separate from the subtotal so the customer can see the price before tax.
Print the blank PDF and fill it in by hand, or send the edited Excel estimate. Before it goes out, check that each row multiplies correctly and the rows add up to your stated subtotal.
Take the estimate with you
Bring the scope, materials and labour together in Construction Job Estimator. Review the breakdown and adjust it to suit the job, with your business details on the quote.
Create an estimate in the app
See how the numbers fit
This example turns an assessed 12 by 20 ft garage into an office to an agreed design. The $12,810 subtotal includes the listed construction packages and a provisional $1,200 heating allowance. Design, permit fees, structural strengthening and utility upgrades are outside this sample price.
Illustrative selling prices in USD. These are example inputs, not local market rates.
| Work / material | Quantity | Rate | Amount |
|---|---|---|---|
| Protection and garage-door removalProtect access and remove the existing garage door; disposal included.1 job × $650 | 1 job | $650 | $650 |
| Specified infill and window packageSupply and fit the front infill and window to the project design; no assumed structural sizing.1 package × $2,600 | 1 package | $2,600 | $2,600 |
| Wall insulation and liningScheduled wall system supplied, installed and finished.1 package × $2,400 | 1 package | $2,400 | $2,400 |
| Insulated floor and finishSpecified floor build-up and finish supplied and installed.240 sq ft × $9 | 240 sq ft | $9 | $2,160 |
| Ceiling packageSpecified insulation, lining and finishing supplied and installed.240 sq ft × $5 | 240 sq ft | $5 | $1,200 |
| Electrical packageFour outlets and three lights at agreed locations, with installation and testing; no service upgrade.1 package × $1,500 | 1 package | $1,500 | $1,500 |
| Heating installation allowanceProvisional selling allowance for the specified heating solution; confirm after assessment.1 allowance × $1,200 | 1 allowance | $1,200 | $1,200 |
| Decoration and final handoverPainting, trim and remaining cleanup; no duplicated garage-door waste charge.1 package × $1,100 | 1 package | $1,100 | $1,100 |
| Subtotal before applicable tax (USD) | $12,810 | ||
Overhead and profit are counted once Every amount is an illustrative customer selling price with overhead and profit already inside it. No second markup is added on top. Each package is all-in, so its labor isn't listed again as a separate line.
Heating is a provisional allowance The $1,200 heating row is included in the subtotal, but it isn't a fixed final price. It's specific to this sample. The row detail says to confirm it after assessment, and your own job may need a different figure.
The packages follow an assessed design The infill, window and insulation packages follow this sample's assessed design. They aren't requirements for every garage. This is a defined construction scope. It doesn't guarantee legal habitable space or an approved change of use, and disposal is covered once, in the door-removal row.
Before you send it
A little clarity here can save a difficult conversation later.
The sample's figures are illustrative and tied to one assessed specification. If you copy $9 per sq ft for the floor without checking your own costs, your price won't reflect your job.
If design, permit fees and structural strengthening aren't written on the estimate, the customer may assume they're covered. Put the exclusions beside the price, where they can't be missed.
A provisional heating figure should read as an allowance to confirm. Also don't add markup on top of a selling price that already includes overhead and profit.
If a package price is all-in, don't add its labor as another line. Likewise, if disposal is in the garage-door removal row, don't charge it again at handover.
Choose what fits your next job
Useful when you want a familiar worksheet and already know the quantities and prices.
Bring job details, measurements and site photos into your estimating workflow on your phone.
A few helpful answers
Yes. Download the blank PDF, completed PDF example and Excel workbook without an account or app installation.
Use the PDF to print and fill in by hand. Choose Excel to edit quantities and selling rates with calculated line amounts, selected-line tax and totals. The workbook includes a separate completed example.
Upload the .xlsx file to Google Drive and open it in Google Sheets. Check the layout and calculations after importing. This is an Excel file, not a hosted Google Sheets copy link.
Yes. Enter your own USD or CAD prices and applicable tax treatment. The example is in USD. Changing the currency label does not convert prices or choose a tax rate.
No. These are illustrative inputs for a fictional job, used to show the document structure and arithmetic. Replace them with inspected quantities and your own selling prices.
No. It's a subtotal before applicable tax. Add tax as a separate line, using whatever applies to your job.
No. Design and permit fees are excluded. The sample is a defined construction scope, not the full cost of securing an approved change of use.
The $1,200 is a provisional allowance in the sample. Once the specified heating solution is confirmed, update that row and tell the customer how the subtotal changes.
Yes. Edit the eight priced rows and the scope notes in Excel. For more line items, use the separate browser editor on this page. The downloadable blank PDF is designed to print and fill in by hand.
Yes. Open the optional browser editor below. Download or print a copy before leaving: the editor does not save entries after a refresh.
Add your job details and review the totals.
Your entries stay in this page. Download a copy before closing; refreshing clears them.