Contractor markup vs margin: the difference in your selling price

Understand markup versus margin with a contractor example, conversion formulas and a cost checklist before setting your job price.

3D contractor comparing costs and selling price using a calculator and coloured blocks

Before you start

  • Markup uses cost as its denominator; margin uses selling price.
  • A 20% markup gives a 16.67% margin on the same cost basis.
  • The amount above an incomplete cost basis is not automatically net profit.

Markup and margin describe the same gap between cost and selling price, but they measure it from different starting points. On a job that costs 1,000, a 20% markup gives a price of 1,200. A 20% margin gives 1,250. Mix them up and your price can land below the amount you meant to recover.

Use the contractor markup calculator to compare both methods. All figures here are illustrative and before tax.

Start with a defined cost basis

Suppose the work costs 1,000 in your chosen currency. Before applying a percentage, decide what that amount includes: materials, labour, subcontractors, equipment, disposal and the overhead you intend the price to recover.

If overhead is missing, the difference between price and entered cost still has to pay it. Calling that entire difference net profit would overstate the result. If overhead is already included, adding the same expense again can overstate the price.

Write down the basis so that every estimate follows the same method.

You also need to bring the job costs together before choosing a markup or margin. Construction Job Estimator pulls materials, labour and other job costs into one estimate, with real-time material prices from local suppliers. You can see the quantities, prices and labour behind each figure and edit any of them, which makes it easier to check what your cost basis includes before you apply a markup or target a margin.

Markup is calculated on cost

With a 20% markup, multiply cost by 1.20:

1,000 × 1.20 = 1,200 selling price.

The amount above cost is 200. Divide 200 by the cost of 1,000 to get the 20% markup. Divide the same 200 by the selling price of 1,200 to get a margin of 16.67%.

Markup is useful when you start with known costs and add an amount to recover the rest of the business requirement. The selected percentage must fit your cost basis; there is no universal percentage supplied by this example.

Margin is calculated on selling price

To obtain a 20% margin, cost must represent 80% of the selling price. Divide by 0.80:

1,000 ÷ 0.80 = 1,250 selling price.

The difference is 250. Dividing 250 by 1,250 gives the intended 20% margin. Relative to the original cost, that is a 25% markup.

The two prices differ by 50 despite both starting with a percentage labelled 20. The denominator explains the difference.

Convert between them

Using percentages as decimals:

  • Margin = markup ÷ (1 + markup).
  • Markup = margin ÷ (1 − margin).
  • Selling price with markup = cost × (1 + markup).
  • Selling price for target margin = cost ÷ (1 − margin).

A target margin of 100% cannot produce a finite selling price from a positive cost. The calculator rejects that input rather than showing a misleading result.

What markup do contractors charge?

There's no single percentage you can copy. The right markup depends on your costs and on what your business needs to earn, so work it out from your own numbers.

Add three annual figures: your direct job costs, your overhead and the operating profit you want. The total is the sales you need. These are illustrative annual budget figures in USD; use your own costs.

  • Direct job costs: 200,000
  • Overhead: 40,000
  • Desired operating profit: 30,000
  • Sales needed: 270,000

That's 70,000 above direct costs. Divide 70,000 by 200,000 and your markup on direct costs is 35%.

Be careful what goes into those figures. Allow for your own working pay when planning costs, rather than treating all of it as profit. Base your overhead and labor rates on realistic billable capacity, because time you can't bill still has to be paid for. Also check that no expense is counted twice, such as in both a labor rate and overhead.

What is a good profit margin for a contractor?

A good margin covers your costs, your overhead and the profit you set as your goal. It won't be the same number for every contractor, so first be clear about which margin you're measuring.

Gross margin is sales minus the cost of sales, divided by sales (BDC's gross profit margin definition). In the example, direct job costs are the cost of sales. Gross profit is 70,000 on sales of 270,000, a gross margin of 25.93%.

That isn't what you keep. Overhead of 40,000 still comes out of the gross profit. What's left is 30,000 operating profit, an operating margin of 11.11% before interest and tax. Net profit comes after interest and tax, and this example doesn't calculate it.

A gross margin can look healthy while operating profit stays thin, if overhead never made it into your price.

How much more than cost should you charge?

It depends on what your cost figure includes. Ask first whether overhead is already in it.

If your cost is direct job costs only, a 35% markup on 200,000 reaches 270,000. That same price gives a 25.93% gross margin. The markup number is bigger because it divides by cost, while margin divides by the selling price.

If your cost base already includes overhead, it's 240,000 (200,000 direct plus 40,000 overhead). You only need a 12.5% markup to reach 270,000, since the extra is just the 30,000 profit. Don't add the 35% again. That counts overhead twice and pushes your price past your target.

Pick one method and write down what your cost base includes, so every estimate follows it.

Treat the result as a cost-based target, not a promise of sales. Compare it with what your finished jobs actually cost, and with what the market and your customer will value. If the target doesn't hold up, review your costs, scope and capacity assumptions before you change the percentage.

Avoid common estimating mistakes

Keep a materials cost separate from a supplier’s supplied-and-fitted selling price. Adding your own installation hours to an all-in package can count the same work twice.

Check your labour rate as well. A wage, a loaded employment cost and a billable selling rate are different inputs. Use the hourly rate calculator when you need to account for paid time, non-billable time and overhead.

Do not apply one percentage to a mixture of costs and final selling prices unless that is an intentional and documented pricing method. Use the material and labour calculator to make the cost stages visible.

Put the final price into the customer estimate

Your internal cost calculation explains how you reached the price. The customer document should explain the work, quantities, inclusions, exclusions and payment arrangements they are agreeing to.

Use the contractor estimate template if you want a standalone document to fill in. If you'd rather prepare the estimate or quote from the same job details you priced, Construction Job Estimator can do that, and it can turn the accepted estimate into an invoice.

← Back to all guides

Construction Job Estimator

Your next estimate.
Ready in minutes.

Tell us what needs doing. Get real-time material prices from local suppliers, bring your labour and other costs together, and send your customer a professional estimate.

Take the next job from description to estimate.

★★★★★ Used by 10k+ contractors