Print and fill it in
A clean, one-page worksheet with task-specific line items and space for scope, exclusions and payment notes.
Download blank PDF Get the completed exampleA clear price. A professional first impression.
Print the blank PDF, open the completed sample, or edit the eight-row Excel file. The sample is a composite deck surface replacement on an assessed existing frame, not a full new-deck price. You can see how a finished estimate reads before you fill in your own.
PDF & Excel · No signup for templates · By Daniel
Prepared for: Sample customer
Scope and exclusions included in the download.
Choose your starting point
Download it now, add your business details and make the numbers your own.
A clean, one-page worksheet with task-specific line items and space for scope, exclusions and payment notes.
Download blank PDF Get the completed exampleEnter your quantities and selling rates. Line amounts, selected-line tax and the total calculate for you.
Download ExcelIncludes a blank template and a completed example.
The details that make it clear
Download a blank PDF to print and fill in, a completed example PDF, or an Excel workbook with formulas and eight editable line rows. Add your business and customer details, describe the scope and exclusions, then enter descriptions, quantities, units and rates. The separate browser editor on this page is another way to prepare your estimate.
Confirm the existing frame suits the chosen decking system before you price it. The sample only works on an assessed frame. Never write the estimate as if a retained frame is a given.
Record your measured size and which edges need fascia. In the sample, 12 × 16 gives 192 sq ft, and one side against the house leaves 40 ft exposed. Your deck will differ.
Write out the cut schedule you will buy, including any spare. The quantity on the row should match the schedule, not a rough area guess.
Match fascia and fastening components to your selected system. Include stock lengths and purchase quantities in the descriptions or scope notes so you can check the takeoff.
Enter hours worked by each person added together, at your own hourly rate. The sample uses 24 plus 6, or 30 person-hours. Don't add a second markup on top of a rate that already includes overhead and profit.
State what is included and what isn't. Write the condition for repricing if inspection or removal shows unsuitable framing. Keep tax, if it applies, on its own line after the subtotal.
From site visit to a clear figure
Describe the surface work you're pricing, then list what is left out. In the sample, footings, framing replacement, structural design, stairs, guardrails and concealed frame repairs are excluded. Add your reprice condition here too.
Measure the deck and exposed edges, then prepare a cut schedule for the selected system. Enter the purchase quantities, units and selling rates. Record important stock lengths and assumptions in the descriptions or scope notes.
Price old surface removal by the unit that suits your job. Add your fasteners and edge details and your cleanup and disposal. If you'd rather not build these rows by hand, Construction Job Estimator turns your spoken or typed job details, your measurements and site photos into a working estimate in minutes. It brings in local supplier prices. You review and adjust quantities, labor and markup, and you still check the scope.
Split labor into decking and fascia or detail work if that helps your customer follow it. Use your own hourly rate. If that rate already carries overhead and profit, don't mark it up again.
Read every row as quantity times rate, then check the subtotal against your job costs. Add applicable tax as its own line. Print the PDF or save the Excel file once the scope and exclusions read the way you want.
Take the estimate with you
Bring the scope, materials and labour together in Construction Job Estimator. Review the breakdown and adjust it to suit the job, with your business details on the quote.
Create an estimate in the app
See how the numbers fit
This is a surface replacement on a 12 by 16 ft deck: 192 sq ft, with an existing frame already assessed as suitable. Old boards are removed, composite decking and fascia installed, and ordinary waste cleared. The illustrative selling price is $4,753 before applicable tax; new framing, stairs and guardrails are excluded.
Illustrative selling prices in USD. These are example inputs, not local market rates.
| Work / material | Quantity | Rate | Amount |
|---|---|---|---|
| Old deck surface removalRemove existing surface boards; frame retained.192 sq ft × $1.50 | 192 sq ft | $1.50 | $288 |
| Composite deck boardsApproved cut schedule: 26 installed 16 ft boards plus one spare.27 boards × $65 | 27 boards | $65 | $1,755 |
| Fascia boardsFour 12 ft stock boards for 40 ft exposed perimeter.4 boards × $85 | 4 boards | $85 | $340 |
| Fasteners and edge detailsSelected system’s specified clips, screws and edge accessories.1 package × $240 | 1 package | $240 | $240 |
| Decking installation laborFit the approved board schedule to assessed frame.24 hours × $65 | 24 hours | $65 | $1,560 |
| Fascia and detail laborFit agreed perimeter fascia and finish details.6 hours × $65 | 6 hours | $65 | $390 |
| Cleanup and disposalOrdinary old-board disposal and final cleanup.1 job × $180 | 1 job | $180 | $180 |
| Subtotal before applicable tax (USD) | $4,753 | ||
The 26-board schedule belongs to this deck The 27 purchased boards are 26 installed 16 ft boards plus one spare. That is an assumed cut schedule for this sample, not an area-to-board formula. Board widths, gaps and edges vary, so build your own schedule from your selected system and your measurements.
Why fascia is bought at 48 ft for a 40 ft edge The exposed perimeter is 12 + 16 + 12 = 40 ft, because the fourth 16 ft side sits against the house. Four 12 ft fascia boards buy 48 ft. The extra length covers cuts and waste, and the row detail says so.
The fasteners package is sample-specific The $240 package covers the clips, screws and edge accessories for the system chosen in this sample. It is a lump sum for this job. Follow your own system's installation guidance when you set yours. Add applicable tax as a separate line after the subtotal.
Before you send it
A little clarity here can save a difficult conversation later.
A surface replacement price only holds if the frame is suitable. Without an assessment and a reprice condition, a bad frame becomes your cost. Put the condition in the scope before the numbers.
That schedule fits one 12 by 16 ft deck and one cut plan. Using it as a formula for another job can leave you short or over-bought. Build the schedule from your own measurements.
The sample's amounts are selling prices with overhead and profit included once. Adding a markup on top of a finished selling price, or listing the same labor again in a package, inflates the price and muddies the estimate.
If stairs, guardrails and structural work aren't written down as excluded, your customer may assume they're covered. List them above the price, in plain words.
Choose what fits your next job
Useful when you want a familiar worksheet and already know the quantities and prices.
Bring job details, measurements and site photos into your estimating workflow on your phone.
A few helpful answers
Yes. Download the blank PDF, completed PDF example and Excel workbook without an account or app installation.
Use the PDF to print and fill in by hand. Choose Excel to edit quantities and selling rates with calculated line amounts, selected-line tax and totals. The workbook includes a separate completed example.
Upload the .xlsx file to Google Drive and open it in Google Sheets. Check the layout and calculations after importing. This is an Excel file, not a hosted Google Sheets copy link.
Yes. Enter your own USD or CAD prices and applicable tax treatment. The example is in USD. Changing the currency label does not convert prices or choose a tax rate.
No. These are illustrative inputs for a fictional job, used to show the document structure and arithmetic. Replace them with inspected quantities and your own selling prices.
No. They're illustrative selling prices for a sample job. Keep the layout and the row logic, then enter your own costs, rates and quantities.
Reprice. The sample's scope says to reprice if inspection or removal shows unsuitable framing. Tell your customer that before work starts, and write it into your own estimate.
They're outside this sample's scope. Add them as separate agreed lines, or write a separate estimate. Keep them out of the surface replacement price so the scope stays clear.
Print the blank PDF and fill it in by hand if you want a paper estimate. Use the Excel file if you want formulas and eight editable rows. The browser editor also supports customization.
Yes. Open the optional browser editor below. Download or print a copy before leaving: the editor does not save entries after a refresh.
Add your job details and review the totals.
Your entries stay in this page. Download a copy before closing; refreshing clears them.