What the worksheet records

The worksheet records quantities only, with no prices. The Excel file has two sheets: Your takeoff, with 12 editable lines, and Completed example. The PDF comes as a blank sheet and a filled one with the same columns, so you can print it and mark it up on site.

Each line has eight fields: Area, Drawing/revision, Item/specification, Unit, Measured quantity, Added allowance, Takeoff quantity, and Notes.

How the sample is filled in

The example is a fictional office lighting package on E-101 revision B, counted from a sample scope rather than an engineered drawing. The open office (L1) has 8 luminaires and 8 mounting kits. The meeting room (L2) has 2 of each. There are 4 boxes as specified. The lighting route conduit shows 110 ft measured plus a 10 ft installation allowance, for 120 ft.

It's a partial lighting package, not a complete electrical installation. Use it to see how a line should look, then replace it with your own scope.

Filling in your own lines

Count devices in each and measure runs in feet or metres, and keep them on separate lines. Luminaires and their mounting kits get their own lines even when the counts match, which makes it easy to spot a missing kit later.

Enter the drawing and revision on every line. If E-101 moves from revision B to C, you can see which lines to recheck.

Copy the specification tag exactly as the drawings or scope show it. Two items with different specs belong on two lines, even if the unit is the same.

Keep the measured quantity and your allowance in separate cells. In the sample, the conduit's extra 10 ft sits in the allowance column, so anyone reading the sheet can see what was measured and what was added. Use Notes to say why. Takeoff quantity is measured plus allowance on each line. If you leave the quantity blank, the result stays blank instead of showing a misleading zero.

The sheet doesn't add a grand total, because 8 each and 120 ft can't be summed into one meaningful number.

What to check before you price it

A clean takeoff only covers what you counted. The sample package still needs separate scope verification for routes, supports, conductors, controls, testing, labor and access. Before you price, go through your sheet and sort every item into one of three groups: counted, assumed, or not yet looked at. Put the open items in Notes so they don't quietly drop out of the price.

Also remember that a takeoff quantity isn't automatically a purchase quantity. Pack sizes and supplier quotes come later, and the number you order may not match the number on this sheet.

The worksheet doesn't size conductors or conduit, design circuits, or check code compliance. Those decisions stay with whoever is qualified to make them. This sheet just keeps your counts and lengths organized.

Turning checked quantities into a price

Once the quantities and scope gaps are settled, you still have to price materials, labor, other job costs and your markup. Construction Job Estimator picks up from there. You describe the job by voice or text, include the measurements you've taken, and add site photos. It builds an editable estimate with real-time local material prices, labor and other costs, such as delivery and equipment hire.

It doesn't measure drawings automatically or design circuits, so the takeoff stays your work. Your checked sheet gives you the numbers to enter. From there you can review the quantities, products, labor time, rates and markup line by line, then prepare a professional estimate or quote for your customer. The app runs on iOS and Android and has a seven-day free trial.

If you'd rather work through the cost side on a template first, there's an electrical estimate template. For the wider method, see how to estimate electrical work.

Ready to price the quantities you checked?

Build your estimate with Construction Job Estimator. Review materials, labor and other job costs, then prepare a professional quote.